Onikom LLC, registered in the Russian Federation by Algerian citizen U.Issam, on February 1, 2001 entered into an agreement on the construction of a hotel complex with Invest-Service OJSC in the territory of the Tyumen Region. The parties also compiled and signed as an annex to the contract an approximate estimate of the work. The deadline for the building of the hotel was set as well - October 1, 2002. The contractor was responsible for providing the construction site with the necessary materials and equipment.
However, the beginning of the work was delayed for two months. In September 2002, the contractor invited the customer to accept and pay for the work performed. During the acceptance process, it turned out that Onikon LLC is trying to hand over an object with deficiencies. The latter appeared (as explained by U. Issam) due to the fact that due to the difficult political situation in Arzhir, the contractor could not make timely delivery of building materials and necessary equipment to the object. In addition, he faced difficulties in obtaining visas for workers to enter the Russian Federation and the harsh climatic conditions of Russia.
It was also found that the contractor almost twice exceeded the approximate estimate and presented for payment the cost of the re-performed roofing work, which he was forced to perform when, due to an accidental fire, part of the roof burned down.
The customer refused to pay for all the work and, declaring that the contractual relationship had been canceled, ordered the construction work of Stroyrem LLC to charge all costs to Onikon LLC.
Analyze the arguments of the parties and decide the case.
However, the beginning of the work was delayed for two months. In September 2002, the contractor invited the customer to accept and pay for the work performed. During the acceptance process, it turned out that Onikon LLC is trying to hand over an object with deficiencies. The latter appeared (as explained by U. Issam) due to the fact that due to the difficult political situation in Arzhir, the contractor could not make timely delivery of building materials and necessary equipment to the object. In addition, he faced difficulties in obtaining visas for workers to enter the Russian Federation and the harsh climatic conditions of Russia.
It was also found that the contractor almost twice exceeded the approximate estimate and presented for payment the cost of the re-performed roofing work, which he was forced to perform when, due to an accidental fire, part of the roof burned down.
The customer refused to pay for all the work and, declaring that the contractual relationship had been canceled, ordered the construction work of Stroyrem LLC to charge all costs to Onikon LLC.
Analyze the arguments of the parties and decide the case.
Additional Information
After payment you will be available a link to the solution of this problem in the file of MS Word. It should be noted that the problem solutions put up for sale were successfully handed over in the period 2003-2018 and could be outdated. However, the general algorithm will always remain true.
Related Products
Solution of the C2 Option 04 Dievskaya VA Malyshev IA
Seller: TerMaster
Solution of the C2 Option 05 Dievskaya VA Malyshev IA
Seller: TerMaster
Dievsky V.A. - Solution of task C2 variant 22 (C2-22)
Seller: Михаил_Перович
Solution K5 B04 termehu of Reshebnik Yablonsky AA 1978
Seller: TerMaster
Solution of the K2 version 07 Dievskaya VA Malyshev IA
Seller: TerMaster
Solution of the C2 Option 14 Dievskaya VA Malyshev IA
Seller: TerMaster
Solution of the C2 Option 08 Dievskaya VA Malyshev IA
Seller: TerMaster
Conflict law test Synergy answers 90/100 points
Seller: sinergey